Option D: Multi-span bridge at Rock Street
- A 172m long, five span bridge.
- Provides a good walking and cycling connection between urban centres
- 3900m of pipeline required. This will result in additional ongoing maintenance and pumping costs compared to other bridge options
- The bridge will span from stop bank to stop bank
- Located in a residential area and would need to be assessed for visual and other impacts
- This option would need a business case to gain Waka Kotahi funding, which will delay the project
- Estimated cost to the Council: $5.6m to $5.8m (assumes 59% funding from Waka Kotahi)
Share Option D: Multi-span bridge at Rock Street on Facebook
Share Option D: Multi-span bridge at Rock Street on Twitter
Share Option D: Multi-span bridge at Rock Street on Linkedin
Email Option D: Multi-span bridge at Rock Street link
We will be looking further into the option of putting the pipelines under the Mataura River. Thanks for taking part in this project.