Option C: Multi-span bridge at Halton Street

  • A 225m long, five span bridge.
  • Provides good walking and cycling connections for the community
  • 3300m of pipeline required, more than double that of the Maitland Street option. This will likely result in additional ongoing maintenance and pumping costs.
  • The bridge would span from stop bank to stop bank
  • Located in a residential area and would need to be assessed for visual and other impacts
  • Needs a business case to gain Waka Kotahi funding, which will delay the projec
  • Estimated cost to the Council: $5.4m to $5.7m (assumes $2.4m Waka Kotahi funding).
Share Option C: Multi-span bridge at Halton Street on Facebook Share Option C: Multi-span bridge at Halton Street on Twitter Share Option C: Multi-span bridge at Halton Street on Linkedin Email Option C: Multi-span bridge at Halton Street link

We will be looking further into the option of putting the pipelines under the Mataura River. Thanks for taking part in this project.