Option C: Multi-span bridge at Halton Street
- A 225m long, five span bridge.
- Provides good walking and cycling connections for the community
- 3300m of pipeline required, more than double that of the Maitland Street option. This will likely result in additional ongoing maintenance and pumping costs.
- The bridge would span from stop bank to stop bank
- Located in a residential area and would need to be assessed for visual and other impacts
- Needs a business case to gain Waka Kotahi funding, which will delay the projec
- Estimated cost to the Council: $5.4m to $5.7m (assumes $2.4m Waka Kotahi funding).
Share Option C: Multi-span bridge at Halton Street on Facebook
Share Option C: Multi-span bridge at Halton Street on Twitter
Share Option C: Multi-span bridge at Halton Street on Linkedin
Email Option C: Multi-span bridge at Halton Street link
We will be looking further into the option of putting the pipelines under the Mataura River. Thanks for taking part in this project.