Option B: Multi-span bridge at Surrey Street
- A 90m long, three span bridge.
- Provides good walking and cycling connections for the community
- 2950m of pipeline required. This will result in additional ongoing maintenance and pumping costs.
- Requires a cycle/pedestrian pathway in the flood plain
- Located in a residential area and would need to be assessed for visual and other impacts
- Has a high degree of certainty for Waka Kotahi funding. Attracted a 59% funding commitment previously
- Estimated cost to the Council: $4.45m to $4.55m (assumes 59% Waka Kotahi funding)